SPHERE

Deliverables

No.DeliverableDue dateStatus
WP1 – Project management
D1.1Project management plan created and adopted30 Jun 2024completed
D1.2Report on Kick-off meeting31 May 2024completed
D1.3Reports on meetings at mid-term31 Aug 2025not started
D1.4Reports on meetings at the end of the project28 Feb 2027not started
D1.5Tools for management28 Feb 2027in progress
D1.6Progress report31 Aug 2025not started
WP2 – Introduction with key issues for ST in Partner and EU countries
D2.1Reports on analyses key issues related to ST30 Jun 2024completed
D2.2Lists of equipment created30 Jun 2024completed
D2.3Report on analyses existing curricula related to ST31 Jul 2024completed
D2.4Report on ST innovative practices in EU countries31 Aug 2024in progress
WP3 – Development of ST curricula and laboratories
D3.1Catalogue of competences created31 Jan 2025not started
D3.2Report on ST laboratories established28 Feb 2025not started
D3.3Catalogue of courses created31 May 2025not started
D3.4Teaching staff trained31 Oct 2025not started
D3.5Report on undergraduate/master curricula developed31 Jan 2026not started
WP4 – Development of trainings for professionals in the field of transportation
D4.1Reports on survey for transportation stakeholders28 Feb 2025not started
D4.2Reports on trainings for professionals in the field of transportation in EU HEI partners28 Feb 2025not started
D4.3Training materials created31 Aug 2025not started
WP5 – Implementation of ST curricula and trainings
D5.1Students enrolled31 Jan 2026not started
D5.2Professionals in the field of transportation trained31 Aug 2026not started
D5.3Student internships implemented31 Oct 2026not started
D5.4Undergraduate/master curricula implemented28 Feb 2027not started
WP6 – Quality assurance and monitoring
D6.1Quality assurance plan created31 Jul 2024completed
D6.2Report on the Inter-project coaching meeting30 Jun 2025not started
D6.3Internal and external quality report at the mid-term31 Aug 2025not started
D6.4Internal and external quality report at the end of the project28 Feb 2027not started
WP7 – Dissemination and exploitation
D7.1Dissemination and exploitation plan created31 Jul 2024completed
D7.2Sustainability plan created30 Sep 2024in progress
D7.3Project website and social networks created31 May 2024completed
D7.4Project promotional material created31 Aug 2024in progress
D7.5Project website and social networks updated28 Feb 2027not started
D7.6Report on the implementation of the D&E Plan at mid-term31 Aug 2025not started
D7.7Report on the implementation of the D&E Plan at the end of the project28 Feb 2027not started