No. | Deliverable | Due date | Status |
WP1 – Project management |
D1.1 | Project management plan created and adopted | 30 Jun 2024 | completed |
D1.2 | Report on Kick-off meeting | 31 May 2024 | completed |
D1.3 | Reports on meetings at mid-term | 31 Aug 2025 | not started |
D1.4 | Reports on meetings at the end of the project | 28 Feb 2027 | not started |
D1.5 | Tools for management | 28 Feb 2027 | in progress |
D1.6 | Progress report | 31 Aug 2025 | not started |
WP2 – Introduction with key issues for ST in Partner and EU countries |
D2.1 | Reports on analyses key issues related to ST | 30 Jun 2024 | completed |
D2.2 | Lists of equipment created | 30 Jun 2024 | completed |
D2.3 | Report on analyses existing curricula related to ST | 31 Jul 2024 | completed |
D2.4 | Report on ST innovative practices in EU countries | 31 Aug 2024 | in progress |
WP3 – Development of ST curricula and laboratories |
D3.1 | Catalogue of competences created | 31 Jan 2025 | not started |
D3.2 | Report on ST laboratories established | 28 Feb 2025 | not started |
D3.3 | Catalogue of courses created | 31 May 2025 | not started |
D3.4 | Teaching staff trained | 31 Oct 2025 | not started |
D3.5 | Report on undergraduate/master curricula developed | 31 Jan 2026 | not started |
WP4 – Development of trainings for professionals in the field of transportation |
D4.1 | Reports on survey for transportation stakeholders | 28 Feb 2025 | not started |
D4.2 | Reports on trainings for professionals in the field of transportation in EU HEI partners | 28 Feb 2025 | not started |
D4.3 | Training materials created | 31 Aug 2025 | not started |
WP5 – Implementation of ST curricula and trainings |
D5.1 | Students enrolled | 31 Jan 2026 | not started |
D5.2 | Professionals in the field of transportation trained | 31 Aug 2026 | not started |
D5.3 | Student internships implemented | 31 Oct 2026 | not started |
D5.4 | Undergraduate/master curricula implemented | 28 Feb 2027 | not started |
WP6 – Quality assurance and monitoring |
D6.1 | Quality assurance plan created | 31 Jul 2024 | completed |
D6.2 | Report on the Inter-project coaching meeting | 30 Jun 2025 | not started |
D6.3 | Internal and external quality report at the mid-term | 31 Aug 2025 | not started |
D6.4 | Internal and external quality report at the end of the project | 28 Feb 2027 | not started |
WP7 – Dissemination and exploitation |
D7.1 | Dissemination and exploitation plan created | 31 Jul 2024 | completed |
D7.2 | Sustainability plan created | 30 Sep 2024 | in progress |
D7.3 | Project website and social networks created | 31 May 2024 | completed |
D7.4 | Project promotional material created | 31 Aug 2024 | in progress |
D7.5 | Project website and social networks updated | 28 Feb 2027 | not started |
D7.6 | Report on the implementation of the D&E Plan at mid-term | 31 Aug 2025 | not started |
D7.7 | Report on the implementation of the D&E Plan at the end of the project | 28 Feb 2027 | not started |